Hi,
We have a SMS 2003 SP3 hierarchy.
We will be upgrading the hardware for our Central site.
Plan is to backup (SMS site server task) old server to a network share.
Shutdown server.
Join new server to domain with same computer name and IP.
install IIS, SQL, SMS.
Perform restore using Reair Wizard.
Done.

Anything I'm missing, please advise.
Thanks!
  Reply With Quote
Old 05-14-2009, 08:02 AM   #2 (permalink)
Sherry Kissinger [MVP]
Guest
 
Posts: n/a
Default RE: Upgrading Central Site to new hardware

Sounds good. You might want to check out this:
http://www.microsoft.com/downloads/d...displaylang=en


"MAS2009" wrote:

> Hi,
> We have a SMS 2003 SP3 hierarchy.
> We will be upgrading the hardware for our Central site.
> Plan is to backup (SMS site server task) old server to a network share.
> Shutdown server.
> Join new server to domain with same computer name and IP.
> install IIS, SQL, SMS.
> Perform restore using Reair Wizard.
> Done.
>
> Anything I'm missing, please advise.
> Thanks!

  Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On
Forum Jump


All times are GMT. The time now is 09:10 PM.


vBulletin, Copyright ©2000 - 2012, Jelsoft Enterprises Ltd.
2007 - 2012 PackageDeploy.com